CLH opens its new storage facility on the 2nd of December
11.18.2009 - NEWS
CLH (La Compañía Logística de Hidrocarburos ) is progressing with the construction works at its new storage facility at the port of Mahon in Menorca.

The company plans to relocate its current storage activities from the Cala Figuera facility built in 1957 to the new Mahon storage terminal. Once the new storage facility is completed, the Cala Figuera installation will be dismantled. The transfer of Cala Figuera facilites will improve the supply of petroleum products in Menorca.
Building of a new facility required a total investment of 22 million euro and almost two years of work. The new terminal includes 12 tanks with a of total 28.920 m3 built near the airport, a pumping station and a 5.3 km pipeline connecting the tanks with the port’s infrastracture.

Enovos Announces FID on Luxembourg Green Hydrogen Project
06.15.2026 - NEWS
June 15, 2026 [Renewables Now]- Enovos announced that a final investment decision (FID) has been ... Read More
KPC Approves Egypt Gas Project, Output Set for Q4
06.15.2026 - NEWS
June 15, 2026 [Zawya]- Kuwait Petroleum Corporation (KPC) has approved an investment in a gas exp... Read More
Shell Pauses $3 Billion Share Buyback Ahead of ARC Acquisition Vote
06.15.2026 - NEWS
June 15, 2026 [Reuters]- Shell said ‌on Friday it was pausing its $3 billion share buyback prog... Read More
LyondellBasell to Shut Remaining PP Output at Brindisi
06.15.2026 - NEWS
June 15, 2026 [Argus Media]- Petrochemical producer LyondellBasell said it plans to close its rem... Read More