Freeport LNG Working to Place Second LNG Jetty Back in Service
10.04.2023 By Tank Terminals - NEWS

October 4, 2023[LNG Prime]- Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, is working to secure approvals to place back its second jetty in service and to return the export facility to full commercial operations.

 

In February this year, the LNG terminal operator shipped the first cargo from its LNG export plant in Texas since the shutdown in June 2022.

Freeport received regulatory approvals from both the US FERC and PHMSA during the first quarter to restart Phase I operations, which consists of three liquefaction trains, two LNG storage tanks (tanks 1 and 2) and a single LNG jetty (dock 1).

These approvals did not grant authorization to Freeport to commission or place LNG tank 3, Loop 2, and Dock 2 back into service.

In order to continue Freeport’s sequential plan to return the export facility to full commercial operations, Freeport has requested authorization from FERC for the nitrogen cooldown of the Loop 2 LNG rundown piping system and the introduction of hydrocarbons to Loop 2 to complete its cooldown and commissioning.

“These activities are necessary to move into Phase II operations, which would return Dock 2 to service,” Freeport said in a filling with FERC dated September 30.

Freeport noted that any authorization pursuant to this request will be limited to the nitrogen cool down of the Loop 2 LNG rundown piping system and introduction of LNG into the Loop 2 piping.

Subsequent approvals will be necessary to fully return Dock 2 to service, the LNG terminal operator said.

“Given the close coordination that Freeport, PHMSA, and FERC have maintained over the course of the Phase II restoration activities, Freeport would greatly appreciate FERC’s response to this request by October 6, 2023,” it said.

 

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

China Energy to Complete New Serbian Refinery in Four Years - Report
05.20.2024 - NEWS
May 20, 2024 [SeeNews]- China Energy International Group is expected to build a 2.4 billion euro ... Read More
UAE's ADNOC Buys Stake in NextDecade's Rio Grande LNG Facility, Signs Supply Deal
05.20.2024 - NEWS
May 20, 2024 [Reuters]- Abu Dhabi National Oil Company (ADNOC) has acquired an 11.7% stake in Nex... Read More
OMV Petrom Commissioned the Largest Crude Oil Storage Tank in Romania, at Petrobrazi Refinery
05.20.2024 - NEWS
May 20, 2024 [The Diplomat]- OMV Petrom, the largest integrated energy producer in Southeastern E... Read More
Eastern Libya Government Offers Refinery Project to Russian Company
05.20.2024 - NEWS
May 20, 2024 [Oilprice]- The eastern Libyan government has offered Russia’s Tatneft the opportu... Read More