UPDATE 1-Poland's PERN Plans to Extend Gdansk Oil Terminal by 2020
10.15.2018 - NEWS

October 15, 2019 [Reuters] - Poland’s pipeline operator PERN plans to more than double the capacity of Gdansk Oil Terminal, the company said on Monday.

PERN has launched a tender procedure to extend the terminal, which would see its oil storage capacity increase by more than 2.5 million barrels of crude oil from 2.36 million barrels.


PERN plans to build five tanks and complete the investment at the turn of August and September 2020, it said.

It is a second stage of development of the terminal. The first stage, the construction of two oil tanks, is set to be completed in April 2020.

Poland is seeking to reduce its reliance on Russian oil supplies. Its biggest refiner, PKN Orlen, expects a first shipment of Nigerian crude next month, its CEO told Reuters.

“The Polish market is becoming more and more open to deliveries from different suppliers. Our refineries carry out global investments, which allow (the) deepening (of) their processing with the use of crude oil other than Russian,” Igor Wasilewski, president of PERN, said.

—————————-

TankTerminals.com – Research, Market and Expand Your Presence within the Tank Storage Industry. Learn more.

ADNOC Gas Q4 2025 Net Income Decreases 15% to $1.2bn
02.10.2026 - NEWS
February 10, 2026 [Offshore Technology]- ADNOC Gas has reported a net income of $1.17bn for the f... Read More
AI Loses Its Shine as Money Rotates Back Into Big Oil
02.10.2026 - NEWS
February 10, 2026 [Oil Price]- Big Tech plans to spend hundreds of billions on AI this year, the ... Read More
Shell’s Oil Reserves Have Dropped to Lowest Levels Since 2013
02.10.2026 - NEWS
February 10, 2026 [Oil Price]- British Oil and Gas giant Shell Plc. (NYSE:SHEL) needs an explor... Read More
China's LNG Imports Set to Recover in 2026 Though Not to 2024 Level
02.10.2026 - NEWS
February 10, 2026 [Reuters]- China’s liquefied natural gas imports are set to rise in 2026 ... Read More