Shell Defers Prelude LNG Turnaround Due to Industrial Action
08.08.2022 By Ella Keskin - NEWS

August 8, 2022 [Reuters] – Shell Plc said on Monday it is deferring planned maintenance work at the Prelude floating liquefied natural gas (FLNG) facility that was due to go ahead in September because of industrial action at the site off northwest Australia.

 

“As a result of the ongoing Protected Industrial Action and inability to complete preparation work, we are not able to proceed with the planned turnaround at this time,” a Shell spokesperson said in emailed comments.

She said the extensive maintenance work, called a turnaround, would be put off to next year, with the timing to depend on a range of factors including weather conditions, contractor availability and when the industrial action ends.

Shell shut the 3.6-million-tonne-a-year Prelude facility in July and told customers it would be unable to supply LNG cargoes for the duration of protected industrial action – work stoppages approved by Australia’s Fair Work Commission – over a long-running pay dispute.

The Offshore Alliance most recently extended its work stoppages to Aug. 11, fighting to match an April wage deal reached with Inpex Corp (1605.T) at its Ichthys LNG operation.

Shell asked the Fair Work Commission to stop the industrial action and impose a “cooling off period”, which would have allowed it to go ahead with preparations for a turnaround, but the commission rejected the request.

The Offshore Alliance said on Monday it remained willing to enter mediation with Shell. A spokesperson for the Fair Work Commission was not immediately available for comment.

Reporting by Sonali Paul


Pro Trial: Access 11,340 Tank Terminal and Production Facilities

11,340 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Chevron to Supply Hungary with 2 Billion Cubic Metres of LNG, Minister Says
12.17.2025 - NEWS
December 17, 2025 [Reuters]- Hungary’s state-owned MVM group has signed a 5-year deal with ... Read More
Fortum and Kemi Partner to Develop 17-Hectare Hydrogen Project Site on Ajos Island
12.17.2025 - NEWS
December 17, 2025 [Fuel Cells Works]- Fortum and City of Kemi have agreed to develop a site locat... Read More
Vitol Deal Revives Uganda’s $4 Billion Refinery Ambitions
12.17.2025 - NEWS
December 17, 2025 [Oil Price]- Commodity trading major Vitol will provide $2 billion in loans for... Read More
Metafuels Awards McDermott FEED Contract for First Commercial e-SAF Plant in Rotterdam
12.17.2025 - NEWS
December 17, 2025 [Global-eFuels]- Metafuels, the Swiss aviation technology company, has awarded ... Read More