NextDecade Finalizes EPC Contract Refresh for Train 4 and Executes EPC Contract for Train 5 at the Rio Grande LNG Facility
06.13.2025 By Tank Terminals - NEWS

June 13, 2025 [NextDecade]- NextDecade Corporation (NextDecade or the Company) (NASDAQ: NEXT) announced today that its subsidiaries have finalized a pricing refresh of the Company’s lump-sum, turnkey engineering, procurement and construction (EPC) contract with Bechtel Energy Inc. (Bechtel) for the construction of Train 4 and related infrastructure at the Rio Grande LNG Facility and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure at the Rio Grande LNG Facility.

 

Train 4 EPC Contract and Project Costs, and Progress Toward a Final Investment Decision (FID)

Rio Grande LNG Train 4, LLC has agreed to pay Bechtel approximately $4.77 billion for the work under the EPC contract for Train 4. Pricing validity under the Train 4 EPC contract extends through September 15, 2025. NextDecade currently projects that owner’s costs, contingencies, financing fees and interest during construction1 will total approximately $1.8-$2.0 billion for Train 4 and supporting infrastructure, based on current estimates and expected interest rates.

Train 5 EPC Contract, Project Costs, and Progress Toward FID

Rio Grande LNG Train 5, LLC has agreed to pay Bechtel approximately $4.32 billion for the work under the EPC contract for Train 5. Pricing validity under the Train 5 EPC contract extends through September 15, 2025. NextDecade currently projects that owner’s costs, contingencies, financing fees and interest during construction1 will total approximately $1.8-$2.0 billion for Train 5 and supporting infrastructure, based on current estimates and expected interest rates.

Trains 4 and 5 Progress Toward Final Investment Decisions (FIDs)

Commercialization of Train 4 is complete, and the Company has started the financing process for Train 4 and related infrastructure. Subject to obtaining adequate financing, NextDecade expects to achieve a positive FID on Train 4 before the end of the pricing validity period for the Train 4 EPC contract.

NextDecade recently announced a 20-year, 2.0 million tonnes per annum (MTPA) LNG Sale and Purchase Agreement (SPA) with JERA for offtake from Train 5 and is working on commercializing an additional 2.5 MTPA under long-term LNG SPAs to support a positive FID on Train 5. The Company has started the financing process for Train 5 and related infrastructure and, subject to obtaining appropriate commercial support and financing, is targeting FID before the end of the pricing validity period for the Train 5 EPC contract.

 

TankTerminals.com is a market research platform with logistical, operational, infrastructural and shipping data that includes contact details of more than +9,600 tank terminals and +6,000 production facilities worldwide.

Access data. Decide better. See how.

Iraq Starts Developing 70,000 Barrel-Per-Day Refinery in Nineveh
07.17.2025 - NEWS
July 17, 2025 [Iraqi News]- The Iraqi Prime Minister, Mohammed Shia Al-Sudani, initiated on Wedne... Read More
Moeve & Zaffra Sign Memorandum of Understanding to Develop e-SAF Facilities in Spain
07.17.2025 - NEWS
July 17, 2025 [Moeve]- Moeve (formerly Cepsa) and Zaffra, a joint venture between Sasol and Topso... Read More
YPP Corporation to Invest $3.1bn in Kazakhstan Green Hydrogen and Ammonia Project
07.17.2025 - NEWS
July 17, 2025 [H2 View]- South Korean engineering firm YPP Corporation has outlined plans to inve... Read More
New Fortress Energy Signs Five-Year Charter for Energos Winter FSRU with EGAS
07.17.2025 - NEWS
July 17, 2025 [Yahoo Finance]- New Fortress Energy (NFE) has finalised a five-year charter for th... Read More