Massive Boost to Diesel Storage Facilities in Brisbane
02.14.2022 By Ricardo Perez - NEWS

February 14, 2022 [Big Rigs] – Construction has started at the IOR Lytton Terminal to deliver 110 million litres (ML) of new diesel storage to the Brisbane market.

 

Taking place in the Port of Brisbane precinct, the project involves repurposing IOR’s existing 50ML crude oil storage tank for diesel fuel storage and constructing two new tanks with combined capacity of 60ML. Additional construction works for the project include:

    Building a new tanker truck loading area, designed to accommodate up to AB triples.
    Construction of a new wharf deck and marine unloading arm.
    Construction of a 3.2km pipeline (underground and above ground), connecting the terminal to the new wharf deck.
    Construction of all new safety and ancillary systems, including a new containment bund, fire protection, vapour recovery, diesel filtration, and fuel additive injection systems.

The project will create over 260 jobs in construction and prioritise local procurement.

To date, over $14 million in project expenditure has been awarded to local businesses. The total budget for the project is approximately $50 million and IOR expect that up to 90 per cent of this budget will be awarded to Queensland suppliers.

Upon project completion, anticipated for June 2023, the Lytton Fuel Terminal will be Queensland’s largest diesel-only import terminal and a champion for fuel security.

It will supply transport, agriculture, resources and many other industries that are critical to the livelihoods of Queenslanders and Queensland businesses.

To accelerate the completion of the project, the Queensland state government has provided IOR with a $15 million loan.

“We’re extremely grateful for the support we have been provided from the Queensland government. We’re proud to have them onboard as partners in providing fuel security to Queensland,” said Stewart Morland, IOR Petroleum managing director.

The Lytton Terminal facility was built in 1984 and was acquired by IOR in 2008.

The terminal previously stored crude oil received from road tankers and sea carriers berthed at the wharf and transferred crude oil to the neighbouring Ampol Refinery.

Click Here to Access a 10,390 Tank Terminal Database With a Pro Trial

10,390 terminals as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Quatra Expands UK Footprint with Strategic Acquisition of Lifecycle Oils
12.15.2025 - NEWS
December 15, 2025 [Biofuels International]- Quatra, one of Europe’s leading specialists in the ... Read More
KBR Awarded Green Ammonia Project by IGNIS in Spain
12.15.2025 - NEWS
December 15, 2025 [Globe Newswire]- KBR (NYSE: KBR) announced today that it has been awarded a te... Read More
GreenGo Energy and SELECT ENERGY Announce Strategic Partnership for Landmark Green Ammonia Project in Mauritania
12.15.2025 - NEWS
December 15, 2025 [GreenGo Energy]- GreenGo Energy A/S (“GreenGo”), a Danish renewable energy... Read More
Egypt, Qatar's Al Mana Holding Sign $200 Million Sustainable Aviation Fuel Deal
12.15.2025 - NEWS
December 15, 2025 [Reuters]- Egypt signed a contract with Qatar’s Al Mana Holding for a fir... Read More