LNG Canada Pipeline Almost 92 Percent Complete
08.02.2023 By Tank Terminals - NEWS

August 2, 2023 [LNG Prime]- TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 92 percent complete.

 

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update the pipeline has achieved 91.4 percent overall completion and it still expects to complete the project by the end of 2023.

“Our workforce of nearly 4,800 are focused on safely completing remaining critical items across the 670-kilometre project route this summer, while ensuring important environmental management measures are in place,” it said.

“With more than 630 km of pipe installed, crews are busy completing distinct work fronts such as water crossings and steep slopes. To date, more than 92 percent of all classified water crossings are complete, and steep slope areas such as Cable Crane Hill and the Raised Bore, continue to make significant strides forward,” Coastal GasLink said.
Coastal GasLink added that hydrotesting is either complete or underway in every section, a “critically important phase” of the project that ensures it can safely transition its infrastructure into operations.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.
As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is about 85 percent complete and recently completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.
The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.
Shell and its partners and are also evaluating the second phase of the project.

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

UK Waste to Energy, Hydrogen, Carbon Capture Plans Approved
03.21.2025 - NEWS
March 21, 2025 [H2 View]- The North Lincolnshire Green Energy Park (NLGEP) secured a Development ... Read More
Taiwan Signs Up for Alaska LNG Export Project
03.21.2025 - NEWS
March 21, 2025 [Oil Price]- Taiwan’s state-held oil and gas company CPC Corporation on Thursday... Read More
Res Integra to Build 4 MW Green Hydrogen Plant in Sicily
03.21.2025 - NEWS
March 21, 2025 [Rigzone]- IREM SpA’s Res Integra SRL has partnered with Ohmium International In... Read More
Shell Aims to Bring Gas from Venezuela to Trinidad in 2026, Sources Say
03.21.2025 - NEWS
March 21, 2025 [Reuters]- Shell Plc is aiming to begin producing natural gas at Venezuela’s... Read More