Greenstat to Start Construction of Agder Hydrogen Facility in Norway
08.09.2024 By Tank Terminals - NEWS

August 09, 2024 [Offshore Energy]- Norwegian energy company Greenstat is set to commence construction of the Agder hydrogen facility, located at Fiskå industrial park in Kristiansand, Norway.

 

With a planned building period of two years, hydrogen is expected to be available for the maritime and heavy transport sectors by the end of 2026.

Phase 1 of the Hydrogen Hub Agder project, with a capacity of 20 MW and a production of up to 8 tonnes of hydrogen per day, is now being realized in cooperation with multiple partners.

The project, which is 100% owned by Greenstat through Agder Hydrogen Hub, is supported by Elkem, Enova, Kristiansand Municipality, Agder County Municipality, Kristiansand Havn, GCE Node and many more.

La Française de l’Energie (FDE) became the new largest owner of Greenstat early in 2024, and the project thus secured access to the capital that enables the realization of the hydrogen facility, Greenstat noted.

A long-term lease agreement of 30 + 10 years was concluded with the project’s partner Elkem. It covers the lease of the area for the hydrogen plant itself as well as the use of shared services and infrastructure, including a quay, which has already been established in the industrial area at Fiskå.

The project is also supported by NOK 148 million ($14.9 million) investment from Enova.

A contract with Repstad Anlegg has been entered into for foundation work and filling in at sea to prepare for a new quay front to the east. According to Greenstat, it is this work that starts now in August.

Aragon is engaged as an engineering partner and will assist Greenstat’s internal project team with preparing the final design of the hydrogen plant and selecting suppliers of equipment and services.

When the plant is put into operation, it will be possible to offer green hydrogen as a carbon-free maritime fuel for traffic along the Norwegian coast and in the entire North Sea basin, Greenstat said, adding that the production will also be able to go to zero-emission vehicles and construction machinery in the region.

Work is also underway on phase 2 of the project, with a capacity of 40 MW.

To remind, Everfuel transferred its ownership in Agder to Greenstat at the beginning of 2024. At the time, it was also revealed that the final investment decision (FID) on the project had been reached.

 

Free Trial: Access 13,300 Tank Terminal and Production Facilities

13,300 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

BP Partners with Palantir for AI Tech
11.21.2024 - NEWS
November 21, 2024 [Tank Storage]- Palantir Technologies and BP have announced an enterprise agree... Read More
Aramco, Rongsheng Petrochemical Ink Deal to Progress Saudi Refinery Project
11.20.2024 - NEWS
November 20, 2024 [Rigzone]- Saudi Arabian Oil Co. (Aramco) and Rongsheng Petrochemical Co. Ltd. ... Read More
Stolthaven Terminals Expands in Malaysia to Boost Efficiency and Capacity For Customers
11.20.2024 - NEWS
November 20, 2024 [Stolt-Nielsen]- Stolthaven Westport held an event earlier this month to celeb... Read More
Open Season For CHANE’S Rotterdam Ammonia Import Terminal Development
11.20.2024 - NEWS
November 20, 2024 [Storage Terminals Magazine]- Chane has announced the next phase of decision-ma... Read More