Germany's LNG import Project Plans
11.15.2022 By Ella Keskin - NEWS

November 15, 2022 [Reuters] – Germany is acquiring liquefied natural gas (LNG) terminals as part of its efforts to diversify away from Russian gas.

 

It leased four floating storage and regasification units (FSRUs) in May, capable of importing at least 5 billion cubic metres (bcm) of seaborne gas per year each. The first one was completed in Wilhelmshaven on Nov. 15.

Wilhelmshaven and Brunsbuettel are developed by Uniper UN01.DE and RWE RWEG.DE, respectively.

The Elbe river port of Stade and Lubmin on the Baltic Sea will also receive an FSRU each.

Germany has also formalised the chartering of a fifth floating LNG ship for Wilhelmshaven, the economy ministry said on Oct. 25, ready for the first quarter of 2023.

WILHELMSHAVEN
Uniper in August received approval for the start of construction of an FSRU facility.

Later, facilities to import ammonia and set up an electrolysis plant for turning ammonia into clean hydrogen will be set up at the location.

BRUNSBUETTEL
An FSRU at Brunsbuettel is expected to deliver gas from the end of 2022 or early in 2023 and serve as a forerunner of a fixed LNG facility.

State bank KfW (KFW.UL) and RWE are stakeholders in the fixed facility. Shell (SHEL.L) has committed itself to some guaranteed purchases.

STADE
Project operator Hanseatic Energy Hub (HEH), due to receive an FSRU to go into operation from the end of next year, previously launched invitations to market participants to book regasification capacity at a planned land-based hub.

This could materialise in 2026.

It is backed by gas network company Fluxys (FLUX.BR), investment firm Partners Group (PGHN.S), logistics group Buss and chemicals company Dow (DOW.N).

EnBW (EBKG.DE) has committed itself as a buyer.

Applications for the terminal and port have been submitted. A final investment decision is expected next year.

LUBMIN
The operators of the state-leased FSRU destined for Lubmin expect it to be operational at the end of 2023.

A private consortium, Deutsche ReGas, aims to develop another FSRU hub there earlier and says a recent tender for annual regasification capacity of 11.7 bcm was oversubscribed, with 15.2 bcm sought after.

 

 


Pro Trial: Access 11,340 Tank Terminal and Production Facilities

11,340 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Marathon Petroleum Profit Beats as Margins Rebound from Multi-Year Lows
02.03.2026 - NEWS
February 03, 2026 [Reuters]- Marathon Petroleum reported fourth-quarter profit above Wall Street ... Read More
Dow Announces 2029 Startup of Phase 1 of Its $7.5-B Path2Zero Ethylene Project
02.03.2026 - NEWS
February 03, 2026 [Hydrocarbon Processing]- Dow Inc.’s proposed Path2Zero petrochemical complex... Read More
Frontera to Sell Colombian Assets to Geopark for Up to $400m
02.03.2026 - NEWS
February 03, 2026 [Offshore Technology]- Frontera Energy has signed a definitive agreement to sel... Read More
Equinor Exits Vaca Muerta With $1.1 Billion Sale to Vista Energy
02.03.2026 - NEWS
February 03, 2026 [Oil Price]- Equinor will sell all its assets in Argentina’s Vaca Muerta basi... Read More