Gate terminal to be ready in September 2011
11.30.2010 - NEWS

November 30, 2010 [Bloomberg] - Nederlandse Gasunie NV said the Gate liquefied natural gas terminal under construction in Rotterdam will be ready in September.


“The terminal will be ready by September 2011,” Ulco Vermeulen, Gasunie’s director of business development, said today at the World LNG Summit in Barcelona. “So far we are on time, on quality and on budget.”

Royal Vopak NV is building the terminal with Gasunie, the Dutch state-owned gas distribution company. Gate stands for Gas Access to Europe.

The facility will have three 180,000 cubic meter storage tanks, one jetty and capacity for 12 billion cubic meters of gas a year. The terminal’s throughput capacity may be increased to 16 billion cubic meters.

E.ON Ruhrgas AG, Dong Energy A/S, EconGas GmbH and RWE AG all have import rights at Gate. 

Australia's Woodside Energy Makes Liz Westcott Its Permanent CEO
03.23.2026 - NEWS
March 23, 2026 [Reuters]- Australia’s Woodside Energy on Wednesday named Liz ​Westcott as... Read More
US Lends Oil Companies 45.2 Mln Barrels from Reserve, First Batch of Iran War
03.23.2026 - NEWS
March 23, 2026 [Reuters]- The Trump administration said on Friday it ​has lent 45.2 million bar... Read More
China's Sinopec Posts 36.8% Drop in 2025 Net Profit on Weak Petrochemical Margins, New Energy Substitution
03.23.2026 - NEWS
March 23, 2026 [Reuters]- China Petroleum & Chemical Corp , known as Sinopec, reported a 36.8... Read More
Saudi Aramco Cuts Oil Supply to Asia for Second Month in April
03.23.2026 - NEWS
March 23, 2026 [Reuters]- Saudi Aramco, the world’s top oil exporter, has cut crude supply ... Read More