Fluor Reaches LNG Project Milestone
07.21.2023 By TankTerminals.com News - NEWS

July 21, 2023 [HydrocarbonEngineering]- With the arrival of the last module by ship from its fabrication yard in Zhuhai, China, Fluor Corp. has completed the module fabrication programme on the LNG Canada project in Kitimat, British Columbia, Canada. This milestone marks the completion of a critical phase in the construction of a large terminal for the liquefication, storage and loading of LNG for export to global markets.

 

“Fluor’s role on the LNG Canada Project underscores our commitment to delivering complex energy and chemicals projects for our clients around the world,” said Jim Breuer, group president of Fluor’s Energy Solutions business. “LNG is essential to the energy transition as it displaces higher carbon forms of energy. We are proud to build Canada’s first large LNG export facility, which will support global energy security.”

Fluor, along with its joint venture (JV) partner JGC Corp., is delivering multiple aspects of the LNG Canada project, including engineering, procurement, fabrication and delivery of modules, and construction of the project’s infrastructure and utilities, marine structures and LNG storage tank.

The first major module, measuring 145 ft tall and weighing more than 5000 t, was received in March 2022. Overall, a total of 215 modules of varying sizes have been received and are being set at the project site.

“Completing the module fabrication programme is a major achievement for the LNG Canada Project,” said Pierre Bechelany, President of Fluor’s LNG business. “This accomplishment highlights the success of the innovative approach of modular construction, which has enabled us to advance construction activities onsite while working with local communities, a skilled local workforce, and limiting environmental impacts.”

LNG Canada is a JV between Shell, Petronas, PetroChina, Mitsubishi Corp. and Korea Gas Corp. The project will have an initial capacity to produce 14 million tpy of LNG. The first shipment of LNG is scheduled for mid-decade.

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Aramco Q1 Profit Jumps 25% as Hormuz Risks Push Pipeline to Full Capacity
05.11.2026 - NEWS
May 11, 2026 [Reuters]- Saudi Aramco reported a 25% jump in first-quarter profit on Sunday, showi... Read More
S-Oil Sees Q2 Refining Margins Remaining Healthy Due to High Product Prices
05.11.2026 - NEWS
May 11, 2026 [Reuters]- South Korea’s S-Oil, whose main shareholder is Saudi Aramco, said o... Read More
Woodside Energy's Delayed Browse LNG Project Expected to Cost $35 Billion
05.11.2026 - NEWS
May 11, 2026 [Reuters]- Woodside Energy’s long-delayed Browse liquefied natural gas project... Read More
Oil Market Runs Down Safety Cushion as Supply Shock Worsens
05.11.2026 - NEWS
May 11, 2026 [Oil Price]- The last tankers out of the Persian Gulf are reaching their destination... Read More