Florida LNG Export Project Delayed Five Years Due to Supply Chain Issues
09.13.2024 By Tank Terminals - NEWS

September 13, 2024 [Oilprice]- The U.S. Federal Energy Regulatory Commission (FERC) has extended with five years the September 19, 2024 deadline for Texas-based firm Eagle LNG Partners to build and put into operation a small-scale LNG export facility near Jacksonville, Florida.

 

Eagle LNG Partners has proposed to build and operate an LNG terminal and export facility on the north bank of the St. Johns River in Jacksonville. The original FERC authorization had a deadline of September 19, 2024 for the project to begin operations.

However, due to supply chain hurdles and higher costs, Eagle LNG Partners in July 2024 asked the FERC to grant an extension of time, until September 19, 2029, to construct and place into service its Jacksonville Project.

The original FERC authorization and order required Eagle LNG to complete construction of the project and make it available for service within five years of the date of the order, or by September 19, 2024.

In its request for extension with the FERC, Eagle LNG states that the Jacksonville project has been impacted substantially by the COVID-19 pandemic, which began only six months after the issuance of the order. 

“The COVID-19 pandemic created an extremely challenging environment for the negotiation and execution of contracts. Those impediments continued for some time after the effects of the pandemic had begun to subside in 2022,” the company told FERC.

Eagle LNG also said that inflation and supply chain issues brought on by the pandemic have increased the total installed cost of the project. 

Now the Commission has granted the extension, but the project timeline is slipping by five years and there isn’t a final investment decision on it yet.

Regulatory setbacks have recently plagued larger LNG export projects, too.

Last month, a U.S. appeals court vacated the remand authorization of NextDecade Corporation’s Rio Grande LNG export project in Texas on the grounds that the FERC should have issued a supplemental Environmental Impact Statement (EIS) during its remand process.

 

Free Trial: Access 13,300 Tank Terminal and Production Facilities

13,300 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Big Tech Is Quietly Fueling a Natural Gas Boom
04.11.2026 - NEWS
DATE, YEAR [FUENTE ]- Google’s data center electricity consumption nearly doubled in just a f... Read More
Why US refiners are cashing in as Iran war disrupts oil flows
04.11.2026 - NEWS
Apr, 09, 2026 [ Cryptorank ]- US Gulf Coast refiners are benefiting from some of the strongest ... Read More
European, African crude oil prices hit records on supply disruptions despite ceasefire
04.11.2026 - NEWS
April 9, 2026 [ Reuters ]- European and African crude oil prices climbed to fresh records on W... Read More
Dutch and Belgian Hydrogen Pipelines to be Connected Near Antwerp
04.10.2026 - NEWS
April 10, 2026 [H2 View]- Belgium and the Netherlands are set to link up their hydrogen pipeline ... Read More