Exxon Mobil Says French Refineries Could Take 2-3 Weeks To Fully Restart
10.18.2022 By Ella Keskin - NEWS

October 18, 2022 [Reuters] – Exxon Mobil’s 140,000 barrel per day (bpd) fos-Sur-Mer and 240,000 bpd Port Jerome-Gravenchon oil refineries in France could take 2-3 weeks to fully restart after shutdowns caused by strikes, a company spokesperson said on Tuesday.

 

Strike action over pay at the two refineries, which resulted in a three-week closure, ended late last week.

This has allowed Exxon to begin restarting the plants.

The outages, coupled with walkouts at oil major TotalEnergies (TTEF.PA), contributed to supply problems at French petrol stations and resulted in growing queues of motorists worried about supply disruption.

A nationwide strike in France on Tuesday has not affected the restart of Exxon’s refineries, the spokesperson said.

 

 


Pro Trial: Access 11,340 Tank Terminal and Production Facilities

11,340 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Enovos Announces FID on Luxembourg Green Hydrogen Project
06.15.2026 - NEWS
June 15, 2026 [Renewables Now]- Enovos announced that a final investment decision (FID) has been ... Read More
KPC Approves Egypt Gas Project, Output Set for Q4
06.15.2026 - NEWS
June 15, 2026 [Zawya]- Kuwait Petroleum Corporation (KPC) has approved an investment in a gas exp... Read More
Shell Pauses $3 Billion Share Buyback Ahead of ARC Acquisition Vote
06.15.2026 - NEWS
June 15, 2026 [Reuters]- Shell said ‌on Friday it was pausing its $3 billion share buyback prog... Read More
LyondellBasell to Shut Remaining PP Output at Brindisi
06.15.2026 - NEWS
June 15, 2026 [Argus Media]- Petrochemical producer LyondellBasell said it plans to close its rem... Read More