Crosstex Completes Phase II Expansion Plans for Riverside, LA., Facility
06.27.2013 - NEWS

June 25, 2013 [OPIS] - Crosstex Energy has completed Phase II of its expansion plans at its Riverside facility in southern Louisiana, the company said Wednesday.


This project has raised the capacity of the facility to transload crude from railcars to its barge facility to about 15,000 b/d, the Dallas, Texas-based company also said.

Phase II additions also included a 100,000-b/d above-ground crude storage tank,
a rail spur with a 26-spot crude railcar unloading rack, and a crude offloading facility with pumps and metering as well as a truck unloading bay, they also said.

The Riverside facility also was modified to enable sour crude offloadings in addition to sweet crude, the company added.

The average annual fee-based cash flow from the Riverside expansion projects is expected to be around $10 million beginning in June 2013, Crosstex said.

US LNG opportunities ‘lie beyond Permian basin’
12.07.2025 - NEWS
Dec 04, 2025 [ Gasworld ]- LNG project developers face a critical supply chain challenge that w... Read More
OTTCO affirms strategic role in driving Oman’s hydrogen goals
12.07.2025 - NEWS
December 5, 2025 – [Oman Observer] – Oman Tank Terminal Company (OTTCO), a subsidiar... Read More
Port of Newcastle Completes Feed Studies for Green Hydrogen Project
12.05.2025 - NEWS
December 05, 2025 [Renewables Now]- Port of Newcastle has completed front-end engineering design ... Read More
CHS, Energy Partners Opening New Rail Terminal in Montana
12.05.2025 - NEWS
December 05, 2025 [LPGas Magazine]- When the temperatures drop each winter, Montana propane marke... Read More