Cheniere Completes Train 4 at Corpus Christi Stage 3 LNG Project
12.24.2025 By Tank Terminals - NEWS

December 24, 2025 [Pipeline & Gas Journal]- Cheniere Energy has reached substantial completion on Train 4 at its Corpus Christi Liquefaction Stage 3 project in Texas, marking another milestone in the company’s ongoing LNG expansion.

 

Cheniere said Bechtel, the project’s engineering, procurement and construction contractor, transferred care, custody and control of Train 4 to the company on Dec. 19.

The Stage 3 project consists of seven midscale trains with combined capacity of more than 10 million tonnes per annum and remains ahead of schedule and on budget, Cheniere said. The company expects the remaining three trains to reach substantial completion in 2026.

 

TankTerminals.com is a market research platform with not only manager-level contact details but also logistical, operational, infrastructural and shipping data of more than +10,100 tank terminals and +6,200 production facilities worldwide.

 

Access data. Decide better. See how.

Enbridge Begins Construction on Controversial Line 5 Pipeline Reroute in Wisconsin
04.06.2026 - NEWS
April 06, 2026 [The Pipeline Technology Journal]- Crews have begun clearing trees for a new 41-mi... Read More
Saudi Arabia Sets Record Premium for Flagship Crude as Hormuz Crisis Deepens
04.06.2026 - NEWS
April 06, 2026 [Oil Price]- Saudi Arabia has hiked the price of its flagship Arab Light crude loa... Read More
JGC-Hyundai Joint Venture Considered as EPC Contractor for LNG Project in Papua New Guinea
04.06.2026 - NEWS
April 06, 2026 [LNG Industry]- JGC Holdings Corp. has announced that its overseas EPC operating c... Read More
Naftogaz and Baker Hughes Sign MoU to Develop Production, Transportation, Energy Projects
04.06.2026 - NEWS
April 06, 2026 [LNG Industry]- Naftogaz of Ukraine has signed a memorandum of understanding (MoU)... Read More