Uganda: $5 Billion East Africa Crude Pipeline Now 75% Complete
11.20.2025 By Tank Terminals - NEWS

November 20, 2025 [Pipeline & Gas Journal]- About three-quarters of a $5 billion pipeline crucial for exporting crude oil from Ugandan fields through neighboring Tanzania has been built, Uganda’s state-run sector regulator said on Nov. 19.

 

After nearly two decades of delay, Uganda has now set the second half of next year as the target for starting production from oilfields in its Albertine rift basin in the west of the country.

The 1,443-kilometer (897-mile) East African Crude Oil Pipeline (EACOP) must be finished before production at the $15 billion oil project owned by France’s Total Energies and China’s CNOOC kicks off.

EACOP will connect the Ugandan oilfields to Tanzania’s Indian Ocean Tanga port and has been described as the world’s longest electrically heated crude pipeline.

Ernest Rubondo, chief executive of the Uganda Petroleum Authority which overseas the country’s hydrocarbons sector, said in a statement that all the pipes for the project had been delivered to various stations along the EACOP route.

So far, at least $3.3 billion has been invested in the project, which is 62% owned by TotalEnergies, Rubondo said. Other shareholders include state-owned petroleum firms in Uganda and Tanzania, and CNOOC.

Over $4 billion is being invested in Uganda’s petroleum sector including on activities in the Kingfisher and Tilenga discoveries between 2025-2027 in “preparation for production”, Rubondo said.

Drilling and associated development activity at Tilenga and Kingfisher projects ahead of start of crude production is 60% and 74% complete, respectively, Rubondo said.

 

TankTerminals.com is a market research platform with not only manager-level contact details but also logistical, operational, infrastructural and shipping data of more than +10,100 tank terminals and +6,200 production facilities worldwide.

 

Access data. Decide better. See how.

Port of Newcastle Completes Feed Studies for Green Hydrogen Project
12.05.2025 - NEWS
December 05, 2025 [Renewables Now]- Port of Newcastle has completed front-end engineering design ... Read More
CHS, Energy Partners Opening New Rail Terminal in Montana
12.05.2025 - NEWS
December 05, 2025 [LPGas Magazine]- When the temperatures drop each winter, Montana propane marke... Read More
BPGIC Begins Planning for Fujairah’s First Euro 5-Grade Gasoline Refinery
12.05.2025 - NEWS
December 05, 2025 [Global Flow Control]- Brooge Petroleum and Gas Investment Company (BPGIC), a s... Read More
Var Energi Makes Oil Discovery Near Arctic Field in Norway
12.05.2025 - NEWS
December 05, 2025 [Oil Price]- Var Energi confirmed on Thursday an oil discovery very close to ... Read More