TotalEnergies Tells Mozambique LNG Project Costs Have Risen by $4.5 Billion
10.27.2025 By Tank Terminals - NEWS

October 27, 2025 [Reuters]- TotalEnergies has told Mozambique that the costs of its liquefied natural gas (LNG) project in the country have risen by $4.5 billion in the four years it was on hold, and it wants its production agreement extended by a decade, a letter from its chief executive showed.

 

The French oil major had confirmed on Saturday that together with its partners it had decided to lift force majeure on the project, which was halted in 2021 by an Islamist militant attack and was previously estimated to cost $20 billion.

But before construction can restart, Mozambique’s council of ministers needs to approve an updated budget and schedule.

“This revised budget’s approval shall cover the incremental costs incurred by the project due to the force majeure, which amount to $4.5 billion,” the letter from TotalEnergies CEO Patrick Pouyanne to Mozambique President Daniel Chapo showed.

EXPECTED FIRST PRODUCTION IN FIRST HALF OF 2029

The Southern African country’s oil and gas regulator is coming up with its own estimate of the project’s additional costs and has not said when that will be ready.

Pouyanne’s letter, dated October 24 and seen by Reuters, said the prolonged halt to the project’s development had pushed out the expected first LNG cargo to the first half of 2029, from an initial target of July 2024.

“To compensate partially (for) the economic impact of the extended force majeure … the concessionaire respectfully requires the government to grant an extension of the term of the Golfinho-Atum development and production period … by a duration of 10 years.”

WORK TO CONTINUE IN ‘CONTAINMENT MODE’

TotalEnergies declined to comment. A spokesperson for the Mozambique president did not immediately respond to a request for comment.

The LNG project is 40% complete, although insurgent attacks have shown little sign of abating despite Mozambique signing a new security pact with Rwanda, whose military has helped secure the area where the plant is being developed.

Exxon Mobil is developing a separate project nearby.

The remaining work will take place in “containment mode”, with workers only allowed in by air or sea, TotalEnergies told a September 29 investor day.

Mozambique LNG is owned by TotalEnergies (26.5%), Japan’s Mitsui (20%), ENH (15%), Bharat Petroleum (10%), Oil India (10%), ONGC Videsh (10%) and Thailand’s PTTEP (8.5%).
 

TankTerminals.com is a market research platform with not only manager-level contact details but also logistical, operational, infrastructural and shipping data of more than +9,600 tank terminals and +6,000 production facilities worldwide.

 

Access data. Decide better. See how.

Port of Newcastle Completes Feed Studies for Green Hydrogen Project
12.05.2025 - NEWS
December 05, 2025 [Renewables Now]- Port of Newcastle has completed front-end engineering design ... Read More
CHS, Energy Partners Opening New Rail Terminal in Montana
12.05.2025 - NEWS
December 05, 2025 [LPGas Magazine]- When the temperatures drop each winter, Montana propane marke... Read More
BPGIC Begins Planning for Fujairah’s First Euro 5-Grade Gasoline Refinery
12.05.2025 - NEWS
December 05, 2025 [Global Flow Control]- Brooge Petroleum and Gas Investment Company (BPGIC), a s... Read More
Var Energi Makes Oil Discovery Near Arctic Field in Norway
12.05.2025 - NEWS
December 05, 2025 [Oil Price]- Var Energi confirmed on Thursday an oil discovery very close to ... Read More