Angola's Sonangol Seeks $4.8 Billion to Bridge Lobito Refinery Funding Gap
04.09.2025 By Tank Terminals - NEWS

April 09, 2025 [Reuters]- Angola’s Sonangol is in talks with Chinese and European banks to overcome a $4.8 billion funding shortfall for its planned 200,000 barrel per day Lobito refinery, an executive with the state-owned oil company told Reuters.

 

Angola is Sub-Saharan Africa’s second-biggest crude oil exporter but imports around 80% of its refined products. It has launched a programme to build new refineries and revamp existing facilities to reverse the trend and become a net exporter.

Development of the facility in the Atlantic port city of Lobito was restarted in December 2023 after remaining stalled for almost a decade. When completed, it will be Angola’s largest refinery.

Joaquim Kiteculo, chief executive of Sonangol’s refining division, said the total cost of the project was $6.6 billion, with the single-train refinery with a hydrocracker alone costing $5.3 billion.

“We are not only dealing with Chinese banks, we are looking for other alternatives as well,” he said on the sidelines of an energy conference in Cape Town, South Africa. “We are confident the financing will be raised, and the refinery will go ahead.”

Construction, he said, was expected to start next year.

Kiteculo added Sonangol was in discussions with banks including the Industrial and Commercial Bank of China, Societe Generale, Standard Chartered and Afreximbank.

Sonangol is investing $950 million of its own money during the first phase of Lobito, mainly for infrastructure such as roads and offices. Kiteculo did not say who the other committed investors are.

China National Chemical Engineering Co. Ltd. is the construction and engineering contractor for the refinery. Houston, Texas-headquartered KBR is consulting on the project after preparing the front-end engineering and design work.

“Even though we are still dealing with funding issues we expect to have the mechanical completion for the whole refinery in the first semester of 2027 … and then have the first batch of products and start the commercialisation phase,” Kiteculo said.

He dismissed as untrue recent media reports that Nigeria’s Aliko Dangote, who built the continent’s largest refinery in Nigeria and visited the Angolan capital Luanda recently, was interested in partnering on the Lobito project.

Meanwhile, Kiteculo said an upgrade of Sonangol’s Luanda refinery being carried out in partnership with Italy’s Eni should increase its output from 65,000 bpd to 120,000 by 2028. A separate biorefinery targeting sustainable aviation fuels is also being considered under the partnership, he added.

“We are sure we are going to become one of the major exporters to Africa, including South Africa which is a big consumer market,” he said.

 

Free Trial: Access 13,300 Tank Terminal and Production Facilities

13,300 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

AI Loses Its Shine as Money Rotates Back Into Big Oil
02.10.2026 - NEWS
February 10, 2026 [Oil Price]- Big Tech plans to spend hundreds of billions on AI this year, the ... Read More
Shell’s Oil Reserves Have Dropped to Lowest Levels Since 2013
02.10.2026 - NEWS
February 10, 2026 [Oil Price]- British Oil and Gas giant Shell Plc. (NYSE:SHEL) needs an explor... Read More
China's LNG Imports Set to Recover in 2026 Though Not to 2024 Level
02.10.2026 - NEWS
February 10, 2026 [Reuters]- China’s liquefied natural gas imports are set to rise in 2026 ... Read More
Petredec and Carnot Engines Partner on Next-Generation Engines
02.10.2026 - NEWS
February 10, 2026 [Storage Terminals Magazine]- Petredec, a global leader in the liquefied petrol... Read More