Venture Global LNG's Second Plant Running Over Budget, Document Shows
11.20.2024 By Tank Terminals - NEWS

November 20, 2024 [Reuters]- Venture Global LNG’s second liquefied natural gas export plant, currently under construction in Louisiana, is $2.35 billion over budget and costs could still rise, according to financial documents prepared for its initial public offering of shares.

 

The fast-growing LNG exporter blamed inflationary pressures and costs to keep construction on schedule. The ultimate cost of the Plaquemines LNG facility was projected to reach $21 billion to $22 billion, documents viewed by Reuters show.

The company had no immediate comment.

The 20 million metric tons per annum (MTPA) export facility likely will start producing superchilled gas in coming weeks. It could be one of two new U.S. LNG plants to start operations this year.

Soaring costs for labor, steel and processing equipment have U.S. LNG developers suffering budget overruns and, in some cases, running well behind initial completion schedules.

The Golden Pass LNG join venture between QatarEnergy (QATPE.UL) and Exxon Mobil was more than $2 billion over budget and a year behind schedule when is lead contractor Zachry Holdings (ZHII.UL) filed for bankruptcy and exited the project earlier this year. Operations may begin late next year or early 2026.

Venture Global has covered the $2.35 billion cost overrun and feels it should have enough cash, borrowing capacity and “access to sufficient commissioning cargoes proceeds” to meet further increases, the preliminary IPO documents showed.

The company has said Plaquemines will have a similar commissioning period to its Calcasieu Pass LNG facility, with contract customers likely to receive their first cargoes in 2026 at the earliest, Venture Global LNG CEO Mike Sabel told Reuters in an interview late last year.

Founded 11 years ago by an energy lawyer and investment banker, the company has quickly become a major exporter of liquefied natural gas, competing against larger rivals Cheniere Energy, Freeport LNG and Sempra.

CONTRACT DISPUTES

Venture Global’s Calcasieu Pass 10 MTPA facility is now expected to cost $9.8 billion, inclusive of the repairs to faulty heat recovery steam generator that delayed full commercial operation, the documents show.

Venture Global expects to spend another $343 million to complete the repairs, according to its consolidated balance sheet.

The company is embroiled in contract disputes over the plant startup with, Shell, Edison and Orlen that could cost it hundreds of millions of dollars.

Venture Global has been commissioning Calcasieu Pass since March 2022 and has sold its commissioning cargo on the spot market earning operating profits of $8.4 billion between March 2022 and December 2023, documents show.

 

Free Trial: Access 13,300 Tank Terminal and Production Facilities

13,300 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

India's First Methanol Plant to be Set up in Telangana
11.21.2024 - NEWS
November 21, 2024 [Chem Analyst]- In a groundbreaking initiative, India is set to get its first m... Read More
Egypt in Talks with Foreign Companies Over Long-Term LNG Purchases, Sources Say
11.21.2024 - NEWS
November 21, 2024 [Reuters]- Egypt is in talks with U.S. and other foreign companies to purchase ... Read More
INEOS and GNFC Sign a Memorandum of Understanding to Build a New World Scale Acetic Acid Unit in India
11.21.2024 - NEWS
November 21, 2024 [INEOS]- INEOS Acetyls and Gujarat Narmada Valley Fertilizers & Chemicals L... Read More
Peru's State Oil Firm Could Open to Private Investors in 2025, Chairman says
11.21.2024 - NEWS
November 21, 2024 [Reuters]- Peru’s indebted state-run oil firm could consider offering a ... Read More