NFE Expects to Launch Altamira LNG Production in March
02.29.2024 By Tank Terminals - NEWS

February 29, 2024 [LNG Prime]- US LNG firm New Fortress Energy expects to start production of liquefied natural gas at its first FLNG project off Altamira, Mexico in March.

 

The Wes Edens-led firm announced this in its fourth-quarter results report issued on Thursday.

NFE is now expecting “first LNG in March and first cargo in April 2024, it said.

In its latest update in November 2023, NFE said it completed “sailaway, installation, and first gas for our first FLNG asset in offshore Altamira, Mexico.”

The company said in its third-quarter report it expected to achieve first LNG and to reach full commercial operation by the end of the fourth quarter last year.

Prior to that, the firm delayed the launch of the project and in an update on September 29 said that it planned to launch the FLNG project off Altamira in late October or early November.

NFE sent its liquefaction rig Pioneer II on September 26, 2023 to Mexico’s Altamira to start serving the FLNG project.

Prior to this, NFE’s utilities and accommodation rig, Pioneer III, arrived off Altamira, as well as the gas treatment rig.

The $1.3 billion FLNG project consists of three rigs, Pioneer I, II, and III.

Besides the three rigs, the 160,000-cbm Penguin FSU serves the project as a floating storage unit.

 

Second Altamira LNG project

NFE said in the report its has also secured financing commitments of $700 million for its second LNG project located onshore Altamira.

The firm said it expects to complete construction on this project in the first quarter of 2026.

Last year, NFE signed separate deals with CFE and Pemex aimed at installing LNG production units off Mexico.

Under the deal with CFE, the firm agreed to create a new FLNG hub off the coast of Altamira, Tamaulipas.

NFE also signed a letter of intent with CFE to install FLNG units 2 and 3 onshore at the existing Altamira terminal.

In early June last year, the US LNG firm received an export permit for its Altamira Fast LNG facility from Mexico’s Ministry of Energy (SENER).

Under the permit, NFE is authorized to export up to 7.8 million metric tons through April, 2028, providing ample capacity to support the operations of the 1.4 million tons per annum Fast LNG facility through the permitted period, it said.

US Customs and Border Protection has also issued a ruling confirming that the transportation of LNG produced at New Fortress Energy’s FLNG facility located offshore Altamira, Mexico by non-US qualified vessels would not violate the Jones Act.

 

Barcarena FSRU starts operations

NFE also announced on Thursday that its 6 mtpa (300 TBtu) Barcarena LNG terminal located in Para, Brazil is now operational.

The 160,000-cbm FSRU, Energos Celsius, recently arrived at NFE’s terminal in Barcarena following a trip from Singapore.

The converted FSRU, owned by Apollo’s Energos Infrastructure, left Seatrium’s yard in Singapore in December last year.

Moreover, the 2013-built vessel, previously known as Golar Celsius, is on long-term charter to NFE in Brazil.

Energos Celsius has a nominal regasification capacity of 750 million standard cubic
feet per day (mmscfd), up to a maximum capacity of 1,000 mmscfd.

The facility consists of an offshore terminal and FSRU that will supply LNG to several industrial customers, including a 15-year contract with Norsk Hydro’s Alunorte refinery, the largest alumina refinery in the world, NFE said.

NFE expects to immediately begin delivering natural gas to Norsk Hydro’s Alunorte refinery under the gas supply agreement.

The Barcarena terminal will also supply natural gas to NFE’s 630 MW power plant, which is currently under construction adjacent to the Barcarena terminal.

The power plant “remains on track” to achieve COD in the third quarter of 2025 and is about 50 percent complete, it said.

 

Free Trial: Access 13,300 Tank Terminal and Production Facilities

13,300 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

ArcelorMittal Poland Plans to Build a Hydrogen Production Plant in Krakow
11.22.2024 - NEWS
November 22, 2024 [Gmk Center]- An investment of more than PLN 100 million will provide hydrogen ... Read More
Clean Hydrogen Works Awards McDermott FEED Contract for Ascension Clean Energy (ACE) Project
11.22.2024 - NEWS
November 22, 2024 [Mcdermott]- Clean Hydrogen Works (CHW) and McDermott announce that CHW has awa... Read More
MOL Group Signed Cooperation Agreement with KazMunayGas
11.22.2024 - NEWS
November 22, 2024 [World Pipelines]- MOL Group and Kazakhstani national oil company KazMunayGas (... Read More
Dialog's 1Q profit grows 14%, driven by midstream tank storage business and big opex drop
11.22.2024 - NEWS
November 22, 2024 [The Edge Malaysia]- Dialog Group Bhd’s net profit in the first quarter e... Read More