LNG Canada CEO: Start-Up Activities will Take More than a Year to Complete
12.14.2023 By Tank Terminals - NEWS

December 14, 2023 [LNG Prime]- Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

 

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

 

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

CB&I Awarded Contract by TotalEnergies and OQ for Full Containment Liquefied Natural Gas Tank in Oman
05.09.2024 - NEWS
May 09, 2024 [PR Newswire]- CB&I, a wholly owned unrestricted subsidiary of McDermott, has be... Read More
H-TEC SYSTEMS and Bilfinger Join Forces for Green Hydrogen Projects in Europe
05.09.2024 - NEWS
May 09, 2024 [Chem Analyst]- H-TEC SYSTEMS, an innovative leader in PEM electrolysis technology, ... Read More
Chinese Group to Build $1.5bn Green Aviation Fuel Plant in Northern China Based on Wind-Powered Hydrogen
05.09.2024 - NEWS
May 09, 2024 [Hydrogen Insight]- Chinese company Shanxi International Energy Group has signed an ... Read More
Sempra Says ECA LNG Export Project More Than 80 Percent Complete
05.09.2024 - NEWS
May 09, 2024 [LNG Prime]- US LNG exporter Sempra said that construction of the first phase of its... Read More