Construction Progress Continues on Golden Pass LNG Export Plant
12.01.2023 By Tank Terminals - NEWS

December 1, 2023 [LNG Prime]- Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass liquefied natural gas (LNG) export terminal on the US Gulf Coast near Sabine Pass, Texas.

 

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

First train expected to start ops in  2024

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Regarding the start of operations, the FERC said in an inspection report in October that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global expects to launch its Plaquemines LNG facility next year as well.

 

Pro Trial: Access 12,600 Tank Terminal and Production Facilities

12,600 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Sempra Says ECA LNG Export Project More Than 80 Percent Complete
05.09.2024 - NEWS
May 09, 2024 [LNG Prime]- US LNG exporter Sempra said that construction of the first phase of its... Read More
QatarEnergy and Nakilat Enter Long-Term Agreement to Charter and Operate Nine QC-Max Class LNG vessels
05.09.2024 - NEWS
May 09, 2024 [Storage Terminals Magazine]- QatarEnergy has signed a long-term agreement with Qata... Read More
Canadian Utilities Plans C$2 Billion Alberta Natural Gas Pipeline
05.09.2024 - NEWS
May 09, 2024 [Reuters]- Canadian Utilities said on Wednesday it is developing a C$2 billion ($1.4... Read More
ADNOC Signs Third Long-Term Heads of Agreement for Ruwais LNG project
05.09.2024 - NEWS
May 09, 2024 [Storage Terminals Magazine]- ADNOC announced today the signing of a 15-year Heads o... Read More