First Stage of Paldiski LNG Terminal Completed
09.01.2022 By Ella Keskin - NEWS

September 01, 2022 [ The Baltic Times ] – Phase one of the construction of a Liquefied Natural Gas (LNG) terminal in Estonian the port city of Paldiski is to be completed today, Estonian Television (ETV) reports.

The work has gone to plan, Pakrineeme Sadam, the company overseeing the terminal, informs. “This is a mooring pier, to which an almost 400m-long gas tanker, or Floating Storage Regasification Unit (FRSU) ship will be anchored.”

“Following that, a waterborne connection is created via a gas pipeline which connects directly to the [land-based] compressor station and then the Balticconnector [Finland-Estonia undersea gas pipeline],” the company said.

Estonian gas and electricity supplier Elering says the ship-to-shore pipeline will be finished by November 30, while Estonian investors say that the overall facility at Paldiski will be ready earlier than its equivalent on the other side of the Gulf of Finland, at Inkoo.

A spokesperson for Finnish natural gas supplier Gasgrid said that both terminals will be ready by December, providing a choice, meaning Paldiski may remain a back-up terminal for now.

Timo Tatar, deputy secretary general for energy at the Estonian Ministry of Economic Affairs and Communications, said that: “One aspect of the agreement is that over the longer term, this vessel will remain in the market where consumption is higher, which is definitely the Finnish side. Even if the infrastructure here on the Estonian side should end up without a ship for a large part of the time, however, from the point of view of Estonia’s energy security, it will definitely bring an important contribution in any case.”

Latvia also hopes to get deliveries from the Paldiski LNG terminal once it has been constructed.


Pro Trial: Access 11,340 Tank Terminal and Production Facilities

11,340 tank storage and production facilities as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

Koncar, Siemens Energy to Build 22.5 Mln Euro Hydrogen Plant for INA
12.09.2025 - NEWS
December 09, 2025 [SeeNews]- Croatian electrical equipment manufacturer Koncar said on Friday it ... Read More
Cstar Sets January 2026 Start for Kribi Refinery Construction
12.09.2025 - NEWS
December 09, 2025 [Business in Cameroon]- Cstar has announced that an engineering mission will ar... Read More
UAE to Hike LNG Exports to Meet Soaring Global Demand
12.09.2025 - NEWS
December 09, 2025 [Oil Price]- The United Arab Emirates is growing its LNG exports to meet surgin... Read More
Russia Could Boost LPG Exports to China by 40% in 2026, Consultancy Says
12.09.2025 - NEWS
December 09, 2025 [Reuters]- Russia may increase liquefied petroleum gas supplies to China by 40%... Read More