Iran's Strategic Goreh-Jask Oil Pipeline Project Nearing Completion
10.26.2020 By Greta Talmaci - NEWS

October 26, 2020 [Payvand] – Iran’s new 1000-kilometer-long Goreh-Jask oil pipeline in the southern Hormozgan province, which will provide the country with an alternative route for crude oil exports that are currently transferred through the Strait of Hormuz, has registered over 60 percent of physical progress and is underway with full force

.
 
The project, which is aimed at expanding the oil transport capacity in the south of the country to one million barrels a day, was inaugurated in late June by President Hassan Rouhani.
Addressing the inaugural ceremony of the project, President Rouhani said this project was currently the country’s most strategic project.

Rouhani said a total of $300 million has so far been invested in the project while another $800 million to $850 million is needed for its full operation.

“We hope that exports from Jask will begin as the government’s most strategic project by the end of this [calendar] year (March 20, 2021),” the president noted.

According to the head of Iran’s Petroleum Engineering and Development Company (PEDEC), considering the current rate of progress in the Goreh-Jask oil pipeline project, National Iranian Oil Company (NIOC) will be able to export its first oil cargo from Jask terminal by the end of the current Iranian calendar year.

Touraj Dehqani, who visited the project on Sunday, held several meetings with contractors and project managers and was briefed about the details of the project progress; during these meetings, the official emphasized the completion of the project on schedule.

Regarding the overall progress of the project, he said: “The project is being followed up with the aim of completing and launching it before the end of the year, and considering that the project progress has reached about 60 percent, so we focus more on the sectors in which the project operations are facing difficulties and need more attention.”

According to the official, currently, about 650 kilometers (km) of pipes have been provided to the project site.

“It is necessary for pipe manufacturing companies to make extra efforts for timely delivery of the entire length of pipes required for the project within the next three months and send it to the workshop,” he stressed.

Regarding the pump houses No. 2 and 4, which are important parts in the first phase of the project and have priority, more attention has been paid to the supply of required items and deficits. Delivery of the main pumps needed for the launching of this phase is also planned by domestic manufacturers for late November, Dehqani explained.

“Also, in the storage tanks section of Jask terminal, parts of sheets have been made and the welding operations of the tanks have started about one month ago”, the official added.

The PEDEC head also referred to the consequences of the outbreak of the coronavirus and said: “In such circumstances, we have always tried to monitor the health and safety protocols to ensure the health of our colleagues.”

Goreh-Jask pipeline will transfer one million barrels of heavy and light crude oils per day to Jask oil terminal in the southern Hormozgan province to be exported.

————-

Click Here to Access Today a 5,550 Tank Terminal Database With a Pro Trial
5,550 terminals as per the date of this article. Click on the button and register to get instant access to actionable tank storage industry data

NEXTCHEM (MAIRE) Completes the Acquisition of HyDEP and Dragoni Group
05.02.2024 - NEWS
May 02, 2024 [Next Chem]- Further to the announcement made on 21 February 2024, MAIRE (MAIRE.MI)... Read More
INEOS Completes Purchase of LyondellBasell’s Ethylene Oxide and Derivatives Business
05.02.2024 - NEWS
May 02, 2024 [Ineos]- INEOS Oxide and LyondellBasell (LYB) have today completed the sale of LYBâ€... Read More
Trafigura Orders Ammonia Dual-Fuel Gas Carriers
05.02.2024 - NEWS
May 02, 2024 [Splash 247]- Commodities giant Trafigura has contracted four ammonia dual-fuel mids... Read More
Al Masaood Energy And Gecko Robotics Secure Multi-Year Contract With ADNOC Gas
05.02.2024 - NEWS
May 02, 2024 [Storage Terminals Magazine]- Al Masaood Energy and Gecko Robotics have proudly anno... Read More